What the SAT Is โ€” and Where It Fits

The Site Acceptance Test sits between the Factory Acceptance Test and the Installation Qualification in the GAMP 5 validation lifecycle. It is executed at the client's site after the system has been delivered and installed, but before formal IQ testing begins. Its purpose is to confirm that the system survived delivery and installation without damage or configuration loss, and that it is functioning correctly in the actual production environment before the formal qualification record is opened.

The SAT is not always mandatory โ€” the V-model doesn't position it as a formal qualification phase. But in practice, any experienced validation team running a complex PLC/SCADA installation will include one, because it catches the issues that routinely occur during transport and commissioning before they become formal IQ deviations.

SAT vs FAT vs IQ

FAT = system works correctly at the supplier's factory, tested against the FDS. SAT = system works correctly at site after installation, before formal qualification record opens. IQ = formal documented evidence that the system is installed correctly, as a controlled quality record.

SAT POSITION IN THE VALIDATION LIFECYCLE FAT SUPPLIER SITE SHIP SAT CLIENT SITE PRE-IQ IQ FORMAL RECORD OQ OPERATIONAL PQ PERFORMANCE SAT IS INFORMAL โ€” ISSUES FOUND HERE DO NOT BECOME IQ DEVIATIONS. THAT'S THE POINT.
// THE SAT IS YOUR LAST INFORMAL CHECK BEFORE THE FORMAL QUALIFICATION RECORD OPENS. FIND PROBLEMS HERE โ€” NOT IN THE IQ.

What the SAT Tests

The SAT is not a repeat of the FAT. It is specifically targeted at issues that arise during shipping, installation, and site integration โ€” things that were correct at the factory but may have changed in transit or during panel installation:

The Key Difference from IQ: Informal vs Formal

The SAT is executed informally โ€” it is a commissioning activity, not a qualification activity. Issues found during the SAT are corrected before the IQ opens, not logged as IQ deviations. This is the primary reason experienced engineers insist on a SAT: it converts IQ findings into pre-IQ corrections, protecting the formal qualification record.

A wiring error discovered during SAT is fixed and re-checked before IQ. The same error discovered during IQ is a formal deviation, must be logged in the Master Deviation Ledger, requires a corrective action, may delay IQ sign-off, and creates a permanent record of a finding that could raise questions in future audits.

The SAT Protocol

Unlike the FAT, IQ, OQ, and PQ, the SAT protocol does not need to be a formally approved GMP-controlled document. It is typically a working document used by the commissioning team. It should however contain:

In the QLean Framework

The SAT template includes a full I/O loop check sheet (pre-formatted for up to 200 I/O points), network connectivity test table, software version verification record, and a pre-IQ sign-off page. It is designed to be used as a working document during commissioning โ€” not a controlled GMP record โ€” while producing the evidence needed to confirm the system is IQ-ready.